The effective time for working on this project has been November 2006 till March 2007. Nevertheless, this time doesn't only cover the actual development of the planetarium but also common tasks done by all members of the group regarding the Ciclope Astron project in general.
The following table lists the time employed for each of the steps of this project. Common tasks are marked in italics.
| Time | Work | Weeks | Hours/Week | Hours Total |
|---|---|---|---|---|
| Total | 17 | 359 | ||
| 15/11/06 - 15/12/06 |
Collecting Ideas & Features User Interface Design Investigation of existing Web (2.0) Frameworks |
4 | 16 | 64 |
| 15/12/06 - 15/01/07 |
Usage of Google Maps API Existing Planetariums Using existing Applications for Tile Generation (PP3, KStars, Stellarium, Starry Night, Celeastio, Mobile Star Chart) |
5 | 17 | 85 |
| 15/01/07 - 28/02/07 |
Adapting Mobile Star Chart for J2SE and Tile Generation Create Planeatrium Site using Google Maps API Include Functionality for asynchronous Handling of Updates and LookUps Get familiar with GWT and Integrate the Planetarium |
6 | 28 | 168 |
| 28/02/07 - 18/03/07 |
Add Features Correct Problems Write Documentation |
2 | 21 | 42 |